|
| |
|
Once the problem (or problems) that have caused the deterioration of
the concrete have been identified, then proper consideration can be given
to a successful repair. Currently the options are as follows:-
Before approaching concrete repairs, consideration
must first be given to the cause of the problem. This is fundamental to
the success or failure of the repair, and a lack of adequate attention
at this point can jeopardise the whole job.
If the problem has been diagnosed as being due to carbonation
induced or chloride induced corrosion of the reinforcement, patch repairs
may be used, although with the latter, there are precautions needed to
ensure a successful repair. In these notes we shall deal with cracking
and spalling due to reinforcement corrosion only. If the problem has been
diagnosed as due to ASR or any of the other mechanisms of failure, the
repair may need to be specifically designed for that particular contract
and structure, and it is impossible to generalise about the approach which
might be taken.

A
poorly executed patch repair. This was cut out to show that the
contractor did not cut behind the steel, or remove corrosion from the
bar. The life of such a repair is very short indeed.
It must firstly be understood that carbonation is a variable
process and the carbonation front will probably not be uniform over the
structure. Regular testing to determine the cover to the steel reinforcement
and the penetration of carbonation, by the phenolphthalein spray method,
will be required.
Criteria we have employed in the past have been to establish
which areas of concrete fall into the following categories
- Visibly spalled concrete with exposed steel reinforcement.
- Areas which sound hollow when tapped lightly with a club hammer (these
may often be found around actual spalled areas showing the problem is
worse than is visually apparent).
- Areas where the cover to the steel reinforcement is less than 10mm.
- Areas where the carbonation front has encroached to within 5 mm of
the reinforcement. (this necessitates carbonation testing at least every
2 metres or so).
- Areas of honeycombed concrete.
- Areas where the half cell potential values numerically exceed -200
mV (copper/copper sulfate). Using this criterion, however, caution must
be exercised as half cell potentials only show areas of active corrosion.
In the summer, whole areas of corrosion may shut down as the concrete
dries out. Detection of carbonation induced corrosion is not as reliable
as for chloride induced corrosion using the half cell method. If the
above criteria have been followed, half cell potential testing is not
strictly necessary but can be a useful additional aid to diagnosis.
The concrete surface will usually be water jetted prior
to cutting out or lightly grit blasted to remove surface grime and deposits
and this will also often reveal blowholes in the concrete surface.
All of the areas identified above will require breaking
out behind the steel reinforcement, sufficient to get one's fingers behind
the steel, ensuring that the edge of the breakout is cut square and not
"feather edged" which inevitably causes failure of the repairs.
At all locations, the steel must be at very least wire
brushed to remove all loose deposits or preferably grit blasted or water
jetted back to bright metal. If chlorides are present this is essential
and will be dealt with in the next section. If the loss of section of
the steel exceeds a critical amount, it may be necessary to splice in
additional or replacement reinforcement. This decision will be taken by
the Engineer.
Once the area to be repaired has been cut out and cleaned
thoroughly of all debris and dust, the repair can begin. Usually, purpose
designed repair mortars will be used supplied by one of the leading manufacturers.
These usually contain one or more of acrylic or other polymers, shrinkage
compensating additives, silica fume, ggbfs or a variety of other chemical
modifiers to improve workability, permeability, or ease of application.
Simple sand/cement mortars alone should never be used, although
gauging sand and cement with, for example, an SBR polymer emulsion has
been used and can work provided the mortar is correctly batched and gauged
with SBR according to manufacturer's instructions.
It is likely that, for pre batched proprietary repair
mortars, some kind of bonding agent will be specified. These must be applied
strictly in accordance with the manufacturer's instructions, which will
often call for the repair to be applied while the bonding agent is still
wet. If used incorrectly, bonding agents can make very efficient debonding
agents!
If no bonding agent is used, the broken out surface of
the concrete must be thoroughly dampened to kill the suction, ensuring
that the surface is saturated but surface dry at the time of application
of the repair. We have been involved in the investigation of many
failures where the substrate was not adequately wetted and water has been
sucked from the interface of the repair and backing concrete, causing
poor hydration of the cement and failure of the repair.
The repair mortar is then mixed up again following
fully any special instructions from the manufacturer. Repairs are
then usually hand placed packing the mortar on in layers no thicker than
those recommended and using the fingers to pack mortar behind the bar.
Wearing of suitable protective clothing is essential as cementitious repair
mortars are very alkaline and can cause burns or dermatitis. Similarly,
dust masks must be worn when mixing the mortar. The Health and Safety
at Work act and the more recent CDM regulations place very specific responsibilities
on both site operatives and their supervisors and employers to work safely
on site. Once the repair has been filled, a wooden rule is used to level
the repair, and the repair is then floated to a smooth finish with a steel
float. The repair must then be cured in accordance with the manufacturer's
recommendations. This may involve the application of damp hessian or more
usually a spray applied curing membrane.
Once finished and cured, there may be surface irregularities
and blow holes and there will almost certainly be colour variation between
the patch and the surrounding parent concrete. It is usual therefore to
apply a thin skim coat of a proprietary material, usually known as a "fairing
coat" to fill in any surface blemishes and to mask the patches themselves.
This is followed by the application of a final coating of anti-carbonation
paint which has the dual purpose of stopping further carbonation in unrepaired
areas and providing a pleasing and even colour finish.
The coating will require periodic renewal at perhaps
10-15 year intervals.
The problem with chloride induced corrosion is that the
corrosion mechanism is often not fully understood by Engineers and Clients.
Whereas carbonation induced corrosion causes relatively large areas of
the reinforcement to corrode, chloride contamination usually causes very
localised areas of the steel to corrode, which is known as pitting corrosion.
This can result in deep "pits" in the steel surface and considerable
localised loss of section. Often the corrosion deposits are black and
hard and there appears to be little loss of section at first, until the
deposits are either dug out with a penknife, or water jetted clear, when
the full extent of damage can be seen.
Repairing chloride contaminated concrete is similar to
that previously written for carbonation induced corrosion except for several
very important points:-
 |
All corrosion deposits must be removed
by grit blasting or water jetting to bright steel. Failure to do so
leaves chloride contamination behind in the corrosion deposits and
failure will ensue. |
 |
All of the chloride contaminated
concrete must be removed, not just the areas which have spalled or
delaminated. See comments below on the "incipient anode effect." |
 |
A criterion often employed is to repair
all areas where chloride exceeds, say, 0.4% or 0.5% of cement. Strictly,
for chloride added at the time of mixing, the criterion should be
0.4% or for chloride ingressing post hardening, 0.2%. For pre-stressed,
post tensioned or heat cured concrete, the maximum tolerable chloride
level is only 0.1% by mass of cement. |
When an area of steel is corroding under the influence
of chloride contamination, steel is dissolving causing the formation of
iron "ions", tiny charged particles of iron. Simultaneously,
electrons are released which flow along the bar and react at some point
remote from the corrosion with both air and oxygen. Cathodic protection,
which will be discussed in the next section involves providing a small
electric current to the steel which prevents further corrosion. The corroding
areas are supplying electrons to surrounding areas of steel effectively
providing localised cathodic protection to the adjacent steel.
If you now break out a corroding area and apply a patch
repair, without dealing with chloride contamination in adjacent areas,
the cathodic protection system has been removed!!
New corrosion cells will rapidly spring up on either
side of the repair and early failure will often ensue. One manufacturer
uses a sacrificial anode tied to the rebar on either side of the
patch repair. We have recommended this system on several occasions
and it is, for example, installed at a car park in Colchester. We
have published a paper on this project, copies of which are available
free of charge.
The sacrificial anode system can only deal with limited
levels of chloride, up to about 1-1.5%. It can cope with higher
levels, but the lifetime would be reduced. In such cases, chloride
removal (desalination) or impressed current cathodic protection may be viable alternatives.
These repair recommendations are only a guide and apply
only to conventionally reinforced structures. Repair of pre-stressed or
post tensioned structures with tendon damage is a specialist task and
beyond the scope of these notes.
More detailed recommendations, together with specimen
bills of quantities can be found in a Concrete Society Technical Report.
A galvanic cell consists of two different metals (electrodes)
connected through a conducting solution (an electrolyte) and also connected
externally completing a circuit. In such a situation, one of the metals
(the more reactive) will tend to dissolve in the electrolyte while the
other will tend to have new metal deposited on it. In the process of
dissolving, the more reactive metal will liberate electrons which flow
via the external connection (as an electric current) to be used in metal
deposition at the other electrode. The dissolution and deposition reactions
are called half cell reactions; the former is the anode reaction and
the latter is the cathode reaction.
Corrosion is a similar process but with electrode sites
at adjacent locations on the same metal surface. For the corrosion of
steel in concrete, the two half cell reactions are as follows:
1. Iron dissolves forming positively charged iron "ions"
and releasing electrons (e-)
Anodic reaction: Fe ® Fe2+
+ 2e- Equation 1
2. The released electrons migrate along the steel and
react with oxygen and moisture to form hydroxyl ions (OH-)
Cathodic reaction: H2O + ½O2
+ 2e- ® 2OH- Equation
2
The rate of the corrosion process depends upon the
availability of the reactants which are iron (Fe), water (H2O),
oxygen (O2) and electrons (e-). Thus, for example,
if the system is completely dry or starved of oxygen, the steel may
still be active but the corrosion rate will be negligible. The relative
availability of electrons is equivalent to the corrosion current which
depends upon the electrical resistance of the system.
Whether or not the corrosion process can occur at all
depends on the pH of the solution adjacent to the steel which, together
with other conditions such as the availability of reactants, determines
the electrical potential of the steel. Generally, a metal exists in
one of three possible reaction states; passivity, corrosion or immunity
depending on the pH and on the electrical potential of the steel.
Passivity and corrosion are conditions whereby the
above reactions are occurring initially but the Fe2+ (ferrous)
ion is unstable in the presence of oxygen and it will react further
forming ferric oxide. The pH and electrical potential will determine
the physical nature of the ferric oxide formed and thus whether the
iron is corroding or passive.
The corrosion form of iron oxide is expansive, non-adherent
and tends to flake leaving the iron surface exposed to further oxidation.
At more positive potentials, a passive oxide film is formed on the metal
surface. This film is adherent, self repairing and impermeable, limiting
further oxygen access to the metal and effectively halting the corrosion
process.
Immunity occurs at more negative potentials than corrosion
and is a condition whereby the metal has a bright surface and cannot
corrode. So called 'noble metals' like gold and platinum exist in this
condition under normal circumstances but for iron, the electrical potential
needs to be so highly negative that it will cause water to break down
and bubbles of hydrogen gas will be seen on the surface. This is not
the normal condition for steel and will generally only occur where an
external potential is applied to it.
The presence of chloride ions significantly modifies
the corrosion states of metals including iron. For iron the range of
pH and potential for immunity remains the same but the range for general
corrosion is considerably extended. In addition, a different type of
corrosion called pitting corrosion can occur which is intense and localised.
Consequently, the conditions for passivity become severely limited.
The idea of cathodic protection is to artificially
shift the potential of a metal so that it becomes either immune or passive.
In natural soils and waters it is normal to shift the potential of steel
to the immune region whereas for steel in concrete it is preferable
to re-establish passivity.
In sacrificial anode cathodic protection, a galvanic
cell is set up by connecting the steel to a more reactive metal, usually
zinc. The zinc then undergoes the anodic reaction and corrodes whilst
the steel is rendered entirely unreactive because the whole surface
undergoes the cathodic reaction mentioned above and the iron no longer
dissolves. This may also be thought of as the anodic sites on the steel
being shifted to the zinc.
With impressed current cathodic protection, the steel
is connected to the negative terminal of an electrical power supply
forcing it to undergo a cathodic reaction. If the potential of the steel
is made negative enough to make it immune, the cathodic reaction becomes
one whereby water is broken down and hydrogen is liberated as follows:
2H2O +2e- ®
H2 + 2OH- Equation 3
This situation would normally be avoided in concrete
since the pH is high and it is possible to re-establish passivity by
applying a somewhat less negative potential. This consumes considerably
less current and so reduces the cost. The cathode reaction is then as
given in reaction (2) above and the OH- generated helps to
maintain the conditions necessary for passivity.
The anode, connected to the positive terminal of the
power supply, is usually chosen to be a relatively non-reactive conductor
such as carbon or titanium so that its corrosion rate is low. The anode
reaction then generates oxygen and acid (H+) as follows:
H2O ® O2
+ 4H+ + 4e- Equation 4
The current densities normally encountered in CP. systems
are sufficiently low for the amount of acid generated to be safely taken
up by the normal alkalinity of the concrete.
Techniques for the cathodic protection of steel in
concrete vary according to the anode system used. The longest established
system uses cast iron primary anodes over a bridge deck with a conductive
asphalt secondary anode laid over them and an asphaltic concrete wearing
course over that. The system operates at relatively low current densities
with an expected life of 10 to 20 years. It is a low cost, low technology
system which has proved to be highly reliable. Its disadvantage is its
limited application being only suitable for tops of decks.
Conductive coating systems typically contain graphite
in a resin binder and are applied at a thickness of 250 to 400 microns
as a secondary anode. The primary anode consists of thin wires or strips
of titanium laid into the surface beneath the coating. The coating itself
is black but may painted over. The systems operate at medium current
densities with an expected life of 5 to 15 years. An advantage of this
type of system is the range of different surface orientations and shapes
that it can be applied to.
Expanded titanium mesh may be applied as both primary
and secondary anode. This is overlaid often with sprayed concrete, paving
concrete or cast superplasticised mortar. Depending on the grade of
mesh used, the range of current densities may be very large and design
lives of 25 to 100 years or more have been claimed.
The major factor in deciding anode life is the presence
of water due to leakage or permeation through the concrete. Attention
to detail regarding waterproofing of joints and treated concretes can
extend anode life considerably.
Sacrificial flame or arc sprayed zinc has also been
used successfully used in marine locations. These systems are relatively
cheap, require little maintenance and have achieved lifetimes of 8 years
or more. An advantage can be that minimal repairs need to be carried
out to the deteriorated concrete and, in fact, zinc sprayed over exposed
steel is a convenient way of achieving the required electrical contact.
This section is concerned with two recently developed
processes for dealing with corrosion of steel in concrete. Above we
have looked at the mechanisms of corrosion of steel in concrete, and
other methods of dealing with it. Although chloride removal (CR, also
known as chloride extraction and desalination) and realkalisation (ReA)
are relatively new techniques, their use will undoubtedly expand with
time.
We will first see how CR and ReA stop corrosion. We
will then review the advantages and disadvantages of these processes
versus other ways of stopping corrosion such as concrete removal, sealers
and cathodic protection. We will also look at some case histories of
the processes.
The two processes are closely linked, but to avoid
confusion we will deal with the generalities of corrosion, and electrochemical
techniques and then will deal with CR and ReA separately.
We already know that steel is normally passive when
embedded in concrete, due to the alkalinity of the pore water. There
are two ways in which this passivity can he destroyed.
Carbonation
The simplest to understand is by carbonation. Atmospheric
CO2 dissolves in the pore water and forms carbonic acid.
As we know acids react with alkali to form water and a neutral salt,
so the carbonic acid reacts with the calcium hydroxide to form calcium
carbonate:
CO2 + H20 ® H2C03
H2C03 +Ca(OH)2 ®
CaCO3 + 2H20
Once the calcium hydroxide is consumed the pH drops from 13 to 9 and
the passive layer decays. The steel then corrodes in the presence of
the oxygen and water available in the concrete pores.
Chloride attack
The chloride ion attacks the passive layer, even though there is no
drop in pH. Chlorides act as catalysts to corrosion. They are not consumed
in the process, but help to break down the passive layer of oxide on
the steel and allow the corrosion process to proceed quickly.
There is a well known "chloride threshold" for corrosion,
given in terms of the chloride/hydroxyl ratio. When the chloride concentration
exceeds 0.6 of the hydroxyl concentration, then the passive layer will
break down. This approximates to a concentration of 0.4% chloride
by weight of cement. The approximation is because:
 |
Concrete pH (14 - log10 of
the OH concentration), varies with the cement powder and the concrete
mix. A tiny pH' change is a massive change in OH concentration and
therefore the threshold moves radically. |
 |
chlorides can be bound chemically (by
aluminates) and physically (by adsorption on the pore walls). This
removes them (temporarily or permanently) from the corrosion reaction. |
 |
in very dry concrete corrosion may not
occur even at very high Cl- concentration as the water
is missing. |
 |
in saturated concrete corrosion may
not occur even at a very high Cl- concentration as the
oxygen is missing to fuel the corrosion reaction. |
Therefore corrosion can be observed at 0.2% chloride, and none seen
above 1.0% or more. If c) or d) are the reasons, then a change in conditions
may lead to corrosion.
Electrochemical techniques include cathodic protection (CP) chloride
removal (CR) and realkalisation (ReA). They all rely on the fact that
the corrosion process is not merely a chemical one, but also involves
the movement of electrical charge. When steel in concrete corrodes,
it dissolves in the pore water and gives up electrons:
Fe ® Fe2++ 2e- (A)
This is the anodic reaction.
The two electrons must be consumed elsewhere on the steel surface to
preserve electrical neutrality:
2e- +2H20 + 02 ®
40H- (C)
This is the cathodic reaction. You will notice that we are generating
more hydroxyl ions in the cathodic reaction. These ions will strengthen
the passive layer, warding off the effects of carbonation and chloride
ions. You will also note that we need water and oxygen at the cathode
to allow corrosion to occur.
Obviously, if we can make the cathodic reaction predominate along the
steel, we will stop corrosion. In electrochemical techniques we apply
an external anode to the concrete surface. This generates the electrons
instead of the anodic reaction (A), and the steel has only the cathodic
reaction (C) occurring on its surface.. For CR and ReA, the external
anode is temporary, and the reactions are driven by a DC power supply.
The systems re-establish a "passive" environment around the
steel that will last many years.
One requirement for all electrochemical treatment, CR, ReA and cathodic
protection, is good electrical continuity to ensure that current flows
from the anode to all areas of steel. Electrical continuity must be
checked and, if necessary, established in all applications of these
techniques. The reverse side of that issue is that there must not be
short circuits between the steel and the surface. If there is, current
will short circuit the concrete pore structure and the chloride ions
(for CR) and hydroxyl ions (for ReA) will not flow.
We have already determined that the chloride ion is a catalyst to corrosion.
As it is negatively charged we can use the electrochemical process to
repel the chloride ion from the steel surface and move it towards an
external anode.

Anode types
The most popular anode is the same coated titanium mesh used for CP.
Instead of embedding it permanently in a cementitious overlay, a temporary
anode system is used. This is placed inside a cassette shutter, as in
the diagram below. Where the shape of the member is especially difficult,
a sprayed papier maché system can be applied over the anode, soaked
with the electrolyte.
A "sacrificial" anode can be used instead of coated titanium.
Copper was tried in the early 1970s trials, but copper (or its salts)
may accelerate corrosion if its gets into concrete. Steel mesh has been
used more recently but has fallen out of favour as it may be completely
consumed in some areas before the treatment process is over.
Electrolytes
Calcium hydroxide is the usual electrolyte. This has the advantage
over water of being alkaline and stops chlorine gas evolution, although
additional chemicals may be added to increase alkalinity. Lithium salts
have also been used to stop ASR (see below).
End Point Determination
End point determination can be by several means:
Point of diminishing returns - resistance goes up, amount of chloride
removed goes down, when the current is small and the amount of chloride
removed is small, switch off. Switching off for about a week will bring
the system resistance down. But how much more chloride is removed by
allowing "rest" periods is not known.
Direct measurement - take samples from the concrete and when an agreed
level is reached, stop. This assumes that good sampling is possible
and that samples are representative.
Indirect measurement - sample the anode system and or electrolyte.
When chloride level is either at a plateau or an agreed level, stop.
This assumes good sampling.
Experience of charge density needed - measure charge passed (amp hours
per square metre) , and when an agreed limit is reached, switch off.
In practice a combination of systems is used. The experienced contractor
will know the charge density needed and a trial may give a definite
value for a given structure (or element within the structure). Sampling
directly and indirectly will show that the system is responding in the
expected manner. The point of diminishing returns should be reached
soon after the other thresholds.
It is of course impossible to remove all the chlorides from the concrete.
The area immediately around the rebar is almost chloride free, but further
away there is less effect. This is particularly true behind the steel.
Chloride removal will deplete the amount of chloride immediately in
contact with the steel, and will replenish the passive layer. Field
data shows that this is effective for at least six years, but for how
much longer is uncertain. The results suggest about 10 years, but only
real experience will show that.
One implication of the amount of chloride which can be removed is that
if large amounts of chloride have penetrated beyond the steel, or were
cast uniformly into the concrete, then chloride removal will only affect
the chloride level in the "covercrete". The chlorides in the
bulk of the concrete will then diffuse back around the steel and the
corrosion may eventually be re-established. When the process is carried
out, the steel is polarised for some time, perhaps a year, making half
cell potential testing difficult to interpret. The charge on the steel
means, however, that chloride ions will be repelled by the charge during
this time. Thereafter, there will still be a reservoir of negatively
charged hydroxyl ions around the steel, and work is currently being
undertaken to define how long this additional protection remains in
place.
Possible Effects
Passing large amounts of electricity through concrete can have effects
upon its chemistry and therefore its physical condition. Brown staining
around the rebar has been observed on specimens when high currents and
voltages are used (in excess of about 2 or 3 A.m2) This is
an effect on the concrete, not the steel. Current levels are therefore
carefully controlled using an expert management system, with data logging
equipment built into the power supply.
There are two known side effects of CR. The first is the acceleration
of alkali silica reactivity (ASR), and the other is reduction in bond
at the steel concrete interface.
Alkali Silica Reactivity
Research at Aston University here in England and by Eltech Research
in the USA under the SHRP program shows that there can be excess ASR
induced by the cathodic reaction (C) that generates excess alkali at
the steel surface. This is exacerbated by the movement of alkali metal
ions (Na+ and K+) to the steel surface under the
influence of its negative charge. Some researchers in Japan have suggested
that the pH can be so high that the silica gel dissolves, stopping the
expansive process.
Eltech are presently undertaking a field trial to see if that can be
controlled by the application of lithium ions in the electrolyte. Lithium
is known to reduce or stop ASR, and proved effective in lab tests. If
a corroding structure is made with aggregates susceptible to ASR, a
detailed investigation of its likely reaction to CR will be required.
Bond Strength
The effect of current on bond strength of steel in concrete has been
a subject for discussion in the literature for many years, usually with
reference to cathodic protection. In most practical applications, the
major part of the bond is supplied by the ribbing on the bars, so the
details of the performance of the steel/concrete interface is irrelevant.
A feasibility study is presently underway for the application of CR
to a long bridge structure in the North of England. In this case, extensive
use was made of smooth rebars, due to steel shortages at the time of
construction. Some tests have shown that CR reduces bond strength by
as much as 50%. However, careful review of the laboratory data shows
that a large amount of charge was passed to achieve this drop. About
five times as much as is used normally in a CR treatment. A very high
current density was also used.
Work has been carried out by Imperial college that showed reduction
in bond could be a problem with smooth bars, although the effects were
small and in no case did the bond drop below that of the control, uncorroded,
sample. It was considered likely that the lowering of bond was due to
passivation of the corrosion deposits. In any case, spalled concrete,
which is the other alternative is not noted for its bond to steel reinforcement!
Ribbed bars showed no reduction in bond strength.
Why choose Chloride Removal?
One of the major issues facing any consultant or owner of a structure
suffering from chloride induced corrosion is what form of repair to
undertake. There are coatings and sealants, specialised patch repair
materials, options for total or partial replacement, cathodic protection
and now chloride removal.
Since the pores in concrete contain significant amounts of water and
air, sealing it to stop corrosion is unlikely to be effective once chlorides
have penetrated the concrete. This comparatively cheap solution is not
effective once corrosion has started.
Patch repairs are only effective if chloride ingress is local and the
chlorides can all be removed. Just patching up damaged areas is a very
short term palliative (owing to the incipient anode effect), not a long
term rehabilitation. Contaminated concrete must be removed from all
around the steel, and support may be needed during the repair process.
Cathodic protection has been described as the only solution to chloride
induced corrosion that can stop (or effectively stop) the corrosion
process. It has been applied to concrete bridges in the USA since 1973,
and in this country to buildings and other structures since 1988. The
problems with cathodic protection are its requirement for a permanent
power supply, regular monitoring and maintenance.
Chloride removal has the advantage that, like a patch repair, it is
a one off treatment. A generator can be brought in for the duration
of the treatment, so mains power is not needed. There is no long term
maintenance need, but the system does treat the whole structure.
The disadvantage is its unknown duration of effectiveness. We cannot
remove all the chlorides from the concrete. If we can stop further chloride
ingress then the system may be effective for many years (10 to 20).
If chlorides are still impinging on the structure then it will be shorter
(or may require a coating or sealant).
Chloride removal cannot be applied to pre-stressed structures due to
the risk of hydrogen embrittlement. Work is progressing on its application
to structures suffering from ASR, but this is in the early development
stage at the moment. As stated earlier there must be electrical continuity
within the reinforcement network for either of these techniques to be
applied.
Conclusions about Chloride Removal
The origins of chloride removal lay in trials carried out in the 1970's.
It is now being vigorously pursued by the developers of the Norwegian
system, based on the spayed cellulose anode and a major US research
program. Ontario Ministry of transportation now has three trial systems
(two of the Norwegian system, one of the US SHRP researchers) applied.
There is a trial and ongoing monitoring
underway in the UK. Results
are all encouraging.
We do not know how long the treatment process will last, but a range
of five to twenty years is likely, depending upon conditions.
In equations 1 and 2 we saw how carbonic acid reacts with calcium hydroxide
to form calcium carbonate. This removes the hydroxyl ions from solution,
and the pH drops, so that the passive layer is no longer maintained
and corrosion can be initiated.
The cathodic reaction (C) showed that by applying electrons to the
steel, we can generate new hydroxyl ions at the steel surface, regenerating
the alkalinity, and pushing the pH back.
The realkalisation process has been patented, and uses the same cassette
shutter or sprayed cellulose system developed to apply chloride removal.
In addition to generating hydroxyl ions, the developers claim that by
using a sodium carbonate electrolyte they make the treatment more resistant
to further carbonation.

The patent claims that sodium carbonate will move into the concrete
under electro-osmotic pressure. A certain amount will then react with
further incoming carbon dioxide. The equilibrium is at 12.2% of l M
sodium carbonate under atmospheric conditions.
Na2CO3 + CO2 + H20 ®
2NaHCO3
In laboratory tests they have shown that it is very difficult, if not
impossible for a treated specimen to carbonate again. Over 80 realkalisation
treatments (50,000m2) have been undertaken on structures
around Europe over the past few years. The treatment is faster than
chloride removal, only requiring a few days of treatment. Work by Banfill
at Heriot Watt University showed that realkalisation actually improved
the properties of concrete, reducing porosity and permeability, increasing
strength and modulus and not apparently causing any difficulties.
Anode types
Anode types are the same as for chloride removal. Cassette shutters
or sprayed cellulose are used by the owners of the patented system,
with a steel or coated titanium mesh. The steel is more likely to be
used here as the treatment time is shorter and the steel is less likely
to be completely consumed.
Electrolytes
As stated above, sodium carbonate solution is the preferred electrolyte
to give long lasting protection against further CO2 ingress.
However, introducing sodium ions can accelerate ASR so in some cases
just water are used. Also, some problems have been found with adhesion
of coatings when sodium carbonate is used, so the tendency is now to
use a very low dose of sodium carbonate, or just to use water.
In one case a current density of 0.3-0.5A per m2 was applied
(at 12V) to 2000m2 of a building in Norway, with a treatment
time of 3-5 days. In another case 10-22V was applied to give a current
density of 0.4-l.5A/m2 in 12 days on 300m2 of
a bridge control tower in Belgium. A further section of 140m2 was
treated in 9 days with a current of l-2A/m2. All figures
are for concrete surface area. The steel to concrete surface ratio was
not given.
End Point Determination
This is easy for carbonation. A simple measurement of carbonation depth
will show when it has been reduced to zero. Measurement of current flow
also gives guidance and a rapid on site method for measuring sodium
content of dust samples has been developed, where sodium carbonate is
used.
Possible Effects
As there is a smaller charge density applied, the risks of damage are
lower than for chloride removal. As mentioned above, ASR is a risk if
sodium carbonate is used as the electrolyte.
Sodium carbonate can also cause short term efflorescence, and the high
alkalinity after treatment can attack some coatings. Sodium carbonate
will attack oil based paints, varnishes and natural wood finishes.
Case Histories
The patent owners claim that over 80 structures have been treated with
realkalisation around Europe. Two cases are summarised above. A recent
application was completed on 1500m2 roof area of Walthamstow
Magistrates Court. Carbonation depths ranged from 5-25 mm. After treatment
a polymer modified mortar was applied to the surface and an elastomeric
decorative finish applied. The advantage to the Client in this case
was the lack of noise, so the Court could remain in session.
Why choose Realkalisation?
Realkalisation is a simpler treatment than chloride removal. However
the alternative of patching and coating with an anti-carbonation coating
is much more effective than patching and coating for chloride attack.
The extent to which carbonation has reached the rebar, and the requirements
for patch repairing to restore alkalinity will determine whether realkalisation
is preferred either because it is more economic, or in other cases to
avoid the noise, dust and vibration required for extensive patch repairing.
The technique is becoming popular in Europe and the Middle East (in
North America very little attention is paid to carbonation). If the
treatment is as effective as claimed, then the choice between realkalisation
and patching and coating is a question of convenience and cost, together
with a realistic appraisal of the effectiveness of anti-carbonation
coatings.
The patentees and the licensees of the system claim that:
 |
It is financially competitive with the
alternatives. |
 |
There is greatly reduced vibration and
noise. |
 |
All of the surface is treated. |
 |
Guarantees are offered. |
There is no doubt that both these techniques will become established
in the concrete repair field. They have some unique advantages which
will make them the system of choice for some applications. For other
applications they will need to compete financially with other systems.
These materials have seen a dramatic increase in promotion
via manufacturers such as Sika, Balvac, Grace and others. They vary
in mode of use. There are two main types:-
Penetrating liquid or vapour phase corrosion inhibitors (Sika Ferroguard,
Balvac MFP)
Concrete additives such as calcium nitrite, designed to be added to
the concrete at the time of placing, perhaps in conjunction with ggbs,
pfa or silica fume.
The latter have a good track record of successful use in the United
States, employ sound technology, and have been shown by trials to be
effective at dealing with chloride induced corrosion for external sources
of chloride, such as de-icing salt.
The former are materials such as amino-alcohols (Ferroguard), or sodium
monofluorophosphate (MFP). These materials are claimed to deal with
both carbonation induced corrosion, and relatively high levels of chloride.
The technology on which they are based has been successfully used in
the metals industry for many years. They work by inhibiting both the
anodic and the cathodic corrosion reactions, by penetrating in the liquid
or vapour phase down to the steel reinforcement and surrounding the
steel.
Research by various workers has been carried out and it is evident
that in some low risk situations, these materials can have a role in
concrete repair. In our opinion, based upon current research, their
effectiveness is limited to
 |
Concrete suffering from carbonation
with shallow cover, say up to 15mm. Their ability to work with deeper
cover depends on their ability to penetrate adequately to the reinforcement.
This varies from concrete to concrete and cannot be guaranteed. |
 |
Concrete containing up to 0.6% chloride
as chloride ion, by mass of cement. Research has not supported their
effectiveness at higher values. |
Notwithstanding this, repair contracts are being carried out using
a combination of patch repairs, corrosion inhibitors and coatings. In
some cases an insurance backed warranty is being offered, for typically
10 years. Given the combined effectiveness of inhibitors and coatings
together, with existing damage dealt with by patch repair, then if the
warranty is considered acceptable, we see no reason why the Client should
not accept this approach, provided caution is exercised. We would not,
however, consider this approach to be likely to be successful in high
chloride situations. At chloride levels above 1%, specific reassurances
should be sought, in our opinion.
The Author would like to acknowledge the help of Dr John Broomfield
in preparing these notes.
Data from Dr. David Manning of Ontario Ministry of Transportation is
also gratefully acknowledged, as well as background data supplied through
John Broomfield's consultancy work with the Strategic Highway Research
Program.
These acknowledgements do not imply endorsement by any of the persons
or organisations mentioned.
Recommended Reading on Chloride Removal and
Realkalisation
Anderson, Gordon. Chloride extraction and realkalisation of concrete.
Hong Kong Contractor pp 19-25, July-August (1992)
Bennett, J. E.; Schue, T . J. Electrochemical Chloride Removal from
Concrete: A SHRP Contract Status Report. Corrosion 90. April 23-37:
Paper 316 (1990).
Broomfield, John P., SHRP Structures Research. Institute of
Civil Enqineers ICE/SHRP, Sharing the Benefits; 29-31 October 1990;
Tara Hotel, Kensington, London. London: Imprint, Hitchin, Herts; 1990;
ICE 1990: p 35-46.
Electrochemical Chloride Removal and Protection of Concrete Bridge
Components: Laboratory Studies. Strategic Highway Research Program
Report SHRP-S-657, National Research Council, Washington DC 1993.
Jayprakash, G. P.; Bukovatz, J. E.; Ramamurti, K. and Gilliland, W.J.
Electro-osmotic techniques for removal of chloride from concrete
and for emplacement of concrete sealants. Kansas DoT Final Report;
August 1982; FHWA-KS-82-2. (1982)
Lankard, 0. K.; Slater, J. E.; Diegle, K. B.; Martin, C. J.; Boyd,
W. K.; and Snyder, M. J. Development of Electrochemical Techniques
for Removal of Chlorides from Concrete Bridge Decks. Battelle; June
1978; Revised Final Report. (1978)
Lankard, D. R.; Slater, J. E.; Diegle, R. B.; and Boyd, W. K. The
Electrochemical Removal of Chlorides From Concrete: Guide to Materials
and Methodology. Battelle; June (1978).
Lankard, 0. K.; Slater, J. E.; Redden, W. A.; and Neisz, D. E. Neutralisation
of Chlorides in Concrete FHWA-RD 76-60 September (1975).
Miller, J. B. Chloride Removal and Corrosion Protection of Reinforced
Concrete. Strategic Highway Research Program and Traffic Safety
on two Continents, Gothenburg Sweden.; September 29, (1989).
|
| |
|
|